File #: 14-0093    Version: 2
Type: decision Status: Passed
File created: 1/24/2014 In control: City Council
Agenda date: 2/4/2014 Final action: 2/4/2014
Title: Approval of Land Use and Environment Committee 2014 Work Plan and Calendar
Attachments: 1. LUEC Work Plan 2014
Related files: 14-0057
Title
Approval of Land Use and Environment Committee 2014 Work Plan and Calendar
 
Recommended Action
Land Use and Environment Committee Recommendation:
Approve the Land Use and Environment Committee's 2014 Work Plan and Calendar.
 
City Manager Recommendation:
Move to approve the Land Use and Environment Committee's 2014 Work Plan and Calendar
 
Report
Issue:
The Land Use and Environment Committee reviewed and approved for City Council consideration the attached Work Plan and Calendar for 2014 at their January 23, 2014 meeting.  
 
Staff Contact:
Keith Stahley, Director Community Planning and Development Department 360.753.8227
 
Presenter(s):
None.  Consent Calendar item.
 
Background and Analysis:
Each year City Council Committee's develop Work Programs and Calendars for City Council consideration.  
 
The proposed Work Plan focuses on supporting City Council's Planning Project Schedule and will include consideration of:
 
1.      Climate Change Resolution - Rich Hoey
2.      Low Barrier Shelter Text Amendment - Leonard Bauer
3.      Boulevard Road Annexation Report and Recommendation -- Todd Stamm
4.      Downtown Project Part III - Brian Wilson, Regular Status Report item with a more extensive report in March and September
5.      Downtown Master Plan Scoping - Leonard Bauer
6.      Comp Plan implementation (Action Plan) - Stacey Ray
7.      Comp Plan Update - Leonard Bauer
8.      Shoreline Master Program Restoration Plan - Stacey Ray
9.      Shoreline Master Program - Keith Stahley, Follow-up after response to City's proposed SMP from DOE
10.      Subarea Planning Process - Leonard Bauer
11.      LID and Land Development Regulation Update and Scoping - Leonard Bauer/Rich Hoey
12.      Parking improvements - lot upgrades and rebranding - Karen Kenneson
13.      Martin Way Planning Process - Sophie Stimson/Cari Hornbein
14.      Planned Action Status Report - Keith Stahley
15.      Annual Annexation Report  - Todd Stamm
16.      Code enforcement status report - Tom Hill
17.      West Olympia Access Study Phase II Scope and IJR Status Report - Mark Russell, TBD  
18.      Water System Plan Update
19.      Waste ReSources Zero Waste Plan Update - Ron Jones
20.      Sustainable Thurston Implementation - Leonard Bauer
21.      Percival Landing Status Report - Paul Simmons
22.      EDDS Update - Fran Eide
23.      Updated Waste Water Regs for Onsite Septic  
24.      Storm and Surface Water Land Acq and Stewardship Strategy - Andy Haub
25.      Urban Forestry Asset Management Plan - Shelly Bentley
26.      Downtown Tree Maintenance - Shelly Bentley
27.      Off-leash Dog Park - Paul Simmons
28.      Downtown Drug Free Zone - Ronnie Roberts
 
Options:
1.      Approve the Work Plan and Calendar as presented.
2.      Approve the Work Plan and Calendar as modified following City Council consideration.
3.      Deny the Work Plan and provide direction to the Land Use and Environment Committee to modify the Work Plan and Calendar as directed by City Council.
 
Financial Impact:
Supported with existing staff resources.