Skip to main content
File #: 21-0782    Version: 1
Type: information Status: Filed
File created: 8/3/2021 In control: Utility Advisory Committee
Agenda date: 8/12/2021 Final action: 8/12/2021
Title: Water System Plan Update Project Briefing
Attachments: 1. Staff Presentation August 12 2021 WSP UAC.pdf
Related files: 23-0733

Title

Water System Plan Update Project Briefing

 

Recommended Action

City Manager Recommendation:

Receive a briefing on the Water System Plan update and provide feedback.

 

Report

Issue:

Receive a briefing on the Water System Plan Update Project.

 

Staff Contact:

Susan Clark, Engineering and Planning Supervisor, Public Works Water Resources, 360.753.8321

 

Presenter:

Susan Clark

 

Background and Analysis:

 

Washington Administrative Code (WAC 246-290-100) requires water utilities with 1,000 or more connections, or those that are expanding, to develop water systems plans every 6 to 10 years.  Water system plans are reviewed and approved by the Washington State Department of Health (DOH) and are formatted to demonstrate the utility’s capacity to remain in compliance with relevant local, state and federal regulations. 

 

The 2015-2020 Water System Plan (WSP) was approved by DOH on January 22, 2016 and our 2021-2026 WSP is due by January 22, 2022.

 

To conduct the update, an internal cross-sectional writing team has been formed. To date, the writing team has:

 

                     Established a project webpage and announced the project in the September/October Five Things Utility Insert

                     Attended a pre-plan meeting with representatives of DOH

                     Determined the focus of our WSP update

                     Reviewed and revised the 2015-2020 WSP goals and objectives  

                     Provided a project briefing to the Utilities Advisory Committee on November 5, 2020

                     Completed a Risk and Resilience Assessment as required by the America’s Water Infrastructure Act of 2018

                     Reviewed and revised the 2015-2020 WSP strategies

                     Completed the Emergency Response Plan update as required by the America’s Water Infrastructure Act of 2018

                     Held a financial analysis project kick-off meeting with our financial consultant

                     Drafted our water use efficiency (conservation) goals

                     Completed a revised water demand forecast and system capacity analysis

                     Completed chapters 1, 2, 4, 5, and 6

 

The following water system planning requirements are pending completion:

                     Hydraulic analysis (of our distribution system)

                     6 and 20-year capital facilities program

                     Financial program

                     Neighboring system and public review period

 

Neighborhood/Community Interests (if known):  None known at this time.  Community outreach, particularly through the Utilities Advisory Committee, will occur as a component of the water system planning process.

 

Options: None at this time. Briefing only.

 

Financial Impact: None at this time. The Water System Plan Update will include a financial and rate analysis and a 6-year and 20-year capital improvement program.

 

Attachments:

None