File #: 16-0494    Version: 1
Type: contract Status: Passed
File created: 4/6/2016 In control: City Council
Agenda date: 5/3/2016 Final action: 5/3/2016
Title: Approval of the Construction Contract for the Maintenance Center and Waste ReSources Building Roof Repairs
Attachments: 1. Construction Contract, 2. Vicinity Map

Title

Approval of the Construction Contract for the Maintenance Center and Waste ReSources Building Roof Repairs

 

Recommended Action

Committee Recommendation:

Not referred to a committee. 

 

City Manager Recommendation:

Move to award the construction contract to Garland/DBS, Incorporated, under the U.S. Communities Cooperative, in the amount of $402,510, and authorize the City Manager to execute all documents necessary to proceed.

 

Report

Issue:

Whether to approve staff’s recommendation to award the construction contract for the Maintenance Center and Waste Resources Building Roof Repairs to Garland/DBS, Incorporated.

 

Staff Contact:

Rick Dougherty, Project Manager, Public Works Engineering, 360.753.8485

 

Presenter(s):

None - Consent Calendar Item.

 

Background and Analysis:

The Maintenance Center roof was installed in 1998 with a 10-year warranty.   The roof has lasted for 18 years.  The Waste ReSources roof was originally installed in 1982.  The roofs have lasted this long due to continued efforts of the city’s Facilities staff.

 

In 2013, the City conducted a ‘Building Condition Assessment’.  The report looked at the Maintenance Center and the Waste Resources roofs.  Our consultant identified the following: 

                     The roofing material shows extreme fatigue; cracking and curling at the seams. 

                     The flashing shows signs of wear and tear.

                     Both roofs need replacement as soon as possible.

 

If City Council approves the award of the contract, construction could begin as early as mid-May and be completed by the end of June, 2016.

 

Neighborhood/Community Interests (if known):

                     New roofs will keep the people and equipment housed in these building dry when it rains.

 

 

 

Options:

1.                     Award the construction contract to Garland/DBS, Incorporated, under the U.S. Communities Cooperative in the amount of $402,510, and authorize the City Manager to execute all documents necessary to proceed.

                     Project can proceed as planned

                     Potential for roof failures and leaks is avoided

                     City realizes cost savings by utilizing the U.S. Communities Cooperative

 

2.                     Do not award the construction contract and direct staff to follow the standard design/bid/build process.

                     Completion of roof repairs delayed

                     Possible damage to City equipment due to leaks

                     Increased project cost in order to follow a design/bid/build process

 

Financial Impact:

The roof repairs are funded through the Building Repair and Replacement Fund (029).  There are sufficient funds to complete the project.

 

                     Project Costs:

                     Construction contract                                                                                                         $402,510

                     10% award contingency                                                                                                         $  40,251

                     City labor                                                                                                                                                   $  60,000

                     Permits                                                                                                                               $       500

                     TOTAL PROJECT COST:                                                                                                         $503,261

                     Total Available Budget:                                                                                                         $600,000

 

Attachments:

1.                     Construction Contract

2.                     Vicinity Map