Title: Approval of a Resolution Authorizing an Amendment to an Agreement with Berger Partnership to Complete Phase 1 Design Services at Yelm Highway Community Park
Attachments: 1. Resolution, 2. Amendment
Title
Approval of a Resolution Authorizing an Amendment to an Agreement with Berger Partnership to Complete Phase 1 Design Services at Yelm Highway Community Park

Recommended Action
Committee Recommendation:
Not referred to a committee.

City Manager Recommendation:
Move to approve a Resolution authorizing an amendment to the contract to Complete Phase 1 Design Services for Yelm Highway Community Park.

Report
Issue:
Whether to approve a Resolution authorizing an amendment to the contract to Complete Phase 1 Design Services for Yelm Highway Community Park.

Staff Contact:
Laura Keehan, Director of Parks Planning & Maintenance, Parks, Arts and Recreation, 360.570.5855

Presenter(s):
None - Consent Calendar Item.

Background and Analysis:
The Yelm Highway Community Park (recently officially named Jolene Unsoeld Community Park) project is completing its final steps prior to construction. The amendment to this contract is to complete final work associated with final design documents, permitting requirements and bid documents preparation. Phase 1 park improvements include:

? Park maintenance office and shop buildings, and supporting elements such as parking, fencing, materials storage, and covered storage.
? One full-size lighted synthetic turf soccer field with all necessary associated items such as netting and goals.
? Thirteen pickleball courts and associated items such as seating, site furnishings, fencing, and gates.
? Two full-size basketball courts.
? One mini-pitch soccer field (Sounders RAVE Foundation funded) and associated interactive play equipment.
? One restroom building that also accommodates storage and food truck support.
? One picnic shelter.
? One approximately 9,000 SF Playground.
? Paved loop pathways.
? All associated furnishings (bike racks, seating, picnic tables).
? One dog park with fencing, gates, and other required amenities.
? One asphalt paved parking lot and one gravel parking lot to support activities at the north end of t...