File #: 12-0749    Version: 1
Type: decision Status: Passed
File created: 11/14/2012 In control: City Council
Agenda date: 12/11/2012 Final action: 12/11/2012
Title: Agenda Item: Approval of Final Construction Costs for the Fire Training Phase 2 Project
Title
Agenda Item:
Approval of Final Construction Costs for the Fire Training Phase 2 Project
Body
Issue:
Changes during construction resulted in higher than projected final project costs, which must be authorized by Council.

Committee Recommendation:
Not referred to a committee.

City Manager’s Recommendation:
Move to authorize the City Manager to approve payment of a total final contract amount of $1,889,035.67 (all applicable tax included) and execute all necessary documents associated with such approval and project close out.

Staff Contact:
Deputy Chief Greg Wright, Project Manager, 360.753.8466

Presenter(s):
None. Consent Calendar item.

Background and Analysis:
In 2011, Council authorized the City Manager to execute a contract with Jones and Roberts Construction, Inc. for Phase Two of the Fire Training Center project.

The project is complete and final costs have exceeded the 10% contingency due to unsuitable soils discovered during construction in one portion of the construction area, wiring and HVAC upgrade in 1/3 of the rehab building and other upgrades that were made to enhance the facility's usefulness and longevity. These upgrades included changes to the in ground fire pump test tank, safety railings, door and window hardware, security lighting and markings, all in an attempt to make the facility more robust for the heavy use a fire training center must be able to withstand over time.

Due to the modifications listed above, the final project cost is $1,889,035. This is above the original contract amount of $1,556,257 (all amounts include all applicable tax). More than sufficient funds are available in the Fire Department's construction account to cover this final project cost.

Factors contributing to the costs:

1. Unforseen conditions discovered during the project: unsuitable soils
Additional costs associated with unsuitable soils - $97,000.

2. Upgrades: upgrade of wiring, HVAC, carpet, and insulation in 1/3 of the rehab building - $127,00...

Click here for full text