Title
Approval of a Resolution Authorizing an Agreement with Berger Partnership to Complete Phase 1 Design at Yelm Highway Community Park
Recommended Action
Committee Recommendation:
Not referred to a committee.
City Manager Recommendation:
Move to approve a Resolution authorizing an agreement with Berger Partnership to complete phase 1 Design at Yelm Highway Community Park.
Report
Issue:
Whether to approve a Resolution authorizing an agreement with Berger Partnership to complete phase 1 Design at Yelm Highway Community Park.
Staff Contact:
Paul Simmons, Parks, Arts & Recreation Director, 360.753.8462
Laura Keehan, Parks Planning & Design Manager, 360.570.5855
Presenter(s):
None - Consent Calendar Item.
Background and Analysis:
The Yelm Highway Community Park project is entering its final step prior to construction. This design contract with Berger Partnership will complete the 30%, 60%, 90% Design/Building Permit, and 100% Design (Drawings, Specifications, Cost Estimate) for the Phase 1 park improvements. Phase 1 park improvements include:
? Park maintenance office and shop buildings, and supporting elements such as parking, fencing, materials storage, and covered storage.
? One full-size lighted synthetic turf soccer field with all necessary associated items such as netting and goals.
? Twelve pickleball courts and associated items such as seating, site furnishings, fencing, and gates.
? Two full-size basketball courts.
? One mini-pitch soccer field (Sounders RAVE Foundation funded) and associated YALP interactive play equipment.
? One restroom building that also accommodates storage, food truck support, and space for the sprayground mechanical and plumbing equipment. This building will be located in a central plaza area that will also accommodate seating, covered bike parking, trash, etc.
? One custom picnic shelter.
? One approximately 7,500 SF Playground.
? One Sprayground: this will be designed and bid as an additive alternate.
? Multiple pave...