Approval of a Resolution Authorizing an Amendment to an Agreement with Berger Partnership to Complete Phase 1 Design Services at Yelm Highway Community Park
Recommended Action
Committee Recommendation:
Not referred to a committee.
City Manager Recommendation:
Move to approve a Resolution authorizing an amendment to the contract to Complete Phase 1 Design Services for Yelm Highway Community Park.
Report
Issue:
Whether to approve a Resolution authorizing an amendment to the contract to Complete Phase 1 Design Services for Yelm Highway Community Park.
Staff Contact:
Laura Keehan, Director of Parks Planning & Maintenance, Parks, Arts and Recreation, 360.570.5855
Presenter(s):
None - Consent Calendar Item.
Background and Analysis:
A note regarding this amendment: Amendment No. 1 to the City's agreement with Berger Partnership for Phase 1 design services for Yelm Highway Community Park, presented at the March 17, 2026 Council meeting, should have totaled $204,216.06 and included an exhibit outlining additional tasks.
An earlier draft was inadvertently attached to the staff report and subsequently executed, reflecting only $18,425 for limited work, whereas the staff report correctly identified the full amount.
Because Amendment No. 1 has been finalized, staff is bringing Amendment No. 2 to address the remaining scope and funding. Amendment No. 2 adds $185,791.06, bringing the total to $204,216.06, with Exhibit A2 detailing the required design and permitting tasks.
The Yelm Highway Community Park (recently officially named Jolene Unsoeld Community Park) project is completing its final steps prior to construction. The amendment to this contract is to complete final work associated with final design documents, permitting requirements and bid documents preparation. Phase 1 park improvements include:
? Park maintenance office and shop buildings, and supporting elements such as parking, fencing, materials storage, and covered storage.
? One full-siz...