Title
Approval of Bid Award for the Boulevard Road and Morse-Merryman Road Roundabout Project
Recommended Action
Committee Recommendation:
Not referred to a committee
City Manager Recommendation:
Move to award the construction contract to Active Construction Inc., in the amount of $3,330,041.90 and authorize the City Manager to execute the contract.
Report
Issue:
Whether to award the construction contract for the Boulevard Road and Morse-Merryman Road Roundabout Project to Active Construction Inc.
Staff Contact:
Jim Rioux, Project Manager, Public Works Engineering, 360.753.8484
Presenter(s):
Jim Rioux, Project Manager, Public Works Engineering, 360.753.8484
Background and Analysis:
In 2006, the City completed the Boulevard Road Corridor Study. The study recommended constructing roundabouts at three intersections to reduce congestion and improve safety for people walking, biking, taking transit, and driving.
The City built the first roundabout at Log Cabin Road in 2010. We completed the second at 22nd Avenue in 2014. This project will construct the third at Morse-Merryman Road.
In addition to the roundabout, the project will include:
? A sidewalk on both sides of the roadway;
? Bike lanes on both sides of the street;
? Ornamental streetlights;
? New water mains;
? Stormwater system improvements, including a new storm pond; and
? Undergrounding all existing power pole-mounted private utilities.
Neighborhood/Community Interests (if known):
Completing this project will significantly improve safety and mobility along the corridor.
Construction activities will have a significant impact on a very busy intersection. The contractor and City staff will provide alternative route information throughout construction.
If Council awards the contract, the project will start in September of this year. This ensures that we will start construction in time to meet grant requirements. Construction activities this year will be limited to site preparation an...