File #: 17-0471    Version: 1
Type: contract Status: Passed
File created: 4/21/2017 In control: City Council
Agenda date: 6/13/2017 Final action: 6/13/2017
Title: Approval of Bid Award for the 2017 Pavement Preservation Project
Attachments: 1. Summary of Bids, 2. Vicinity Map
Title
Approval of Bid Award for the 2017 Pavement Preservation Project

Recommended Action
Committee Recommendation:
Not referred to a committee.

City Manager Recommendation:
Move to award the construction contract to Doolittle Construction, in the amount of $879,316, and authorize the City Manager to execute the contract.

Report
Issue:
Whether to award the construction contract for the 2017 Pavement Preservation Project to Doolittle Construction.

Staff Contact:
Fran Eide, P.E., City Engineer, Public Works Engineering, 360.753.8422

Presenter(s):
None - Consent Calendar item.

Background and Analysis:
This year marks the 18th year of the Least Cost Pavement Preservation Program for the City. The program purpose is to extend the overall life of streets. Pavement preservation methods include: crack seal, microsurfacing, and chip seal. This approach reduces the overall cost of maintaining City streets and keeps them in fair or better condition.

This project will use chip seal to improve approximately three miles of roadway throughout the City at the following locations;
* Harrison Avenue - Division Street to West Bay Drive
* 14th Avenue NW - Kaiser Road to Walnut Loop
* Walnut Road - Walnut Loop to Division Street
* Cooper Point Auto Mall Drive - US 101 to Black Lake Boulevard
* State Avenue* - Quince Street to Tullis Street

*One lane of the recently paved section of State Avenue from Quince Street to Tullis Street has cracked and failed in some areas earlier than expected. We believe this occurred because the pavement is thinner in this area, developed small cracks, and rainwater penetrated the surface during our wet winter. Chip sealing the southern lane in this area should help prevent further deterioration of the pavement surface.

We anticipate starting construction in July and ending by September, 2017.

Neighborhood/Community Interests (if known):
The community should expect delays for people driving, biking, and walking throughout the ...

Click here for full text