File #: 18-0852    Version: 1
Type: contract Status: Passed
File created: 9/4/2018 In control: City Council
Agenda date: 10/16/2018 Final action: 10/16/2018
Title: Approval of Bid Award for the Priority Sewer Repairs Project
Attachments: 1. Vicinity Map, 2. Bid Summary
Title
Approval of Bid Award for the Priority Sewer Repairs Project

Recommended Action
Committee Recommendation:
Not referred to a committee.

City Manager Recommendation:
Move to award the construction contract to Insituform Technologies, LLC, in the amount of $554,639.68, and authorize the City Manager to execute the contract.

Report
Issue:
Whether to award the construction contract for the Priority Sewer Repairs project to Insituform Technologies, LLC.

Staff Contact:
Jeff Johnstone, P.E., Senior Engineer, Public Works Engineering, 360.753.8290

Presenter(s):
None - Consent Calendar item.

Background and Analysis:
Water Resources has an ongoing program to identify sewer and storm pipes that are in need of repair. The repair work is part of an annual project to fix problems before pipes need extensive and costly replacement. Repair work consists of lining the pipe using Cured-In-Place Pipe (CIPP) technology.

This project will repair approximately 7,800 feet of pipe at 21 locations throughout the City.

Neighborhood/Community Interests (if known):
The use of CIPP for repairing pipes significantly reduces disruptions to the neighborhood. This method allows the contractor to repair pipes without having to dig open trenches. Streets will remain open during the work. For short periods, one lane may close to complete portions of the work. During these periods, flaggers will direct traffic through the work zone.

The City will communicate with citizens, emergency responders, Intercity Transit, and other stakeholders about the project through Twitter, media releases, and postcards.

Options:
1. Award the construction contract to Insituform Technologies, LLC, in the amount of $554,639.68, and authorize the City Manager to execute the contract.

* The project proceeds as planned.
2. Reject all bids and direct staff to rebid the project.

* The time needed to rebid will delay construction until 2019.
* The cost may increase due to increased staff time to reb...

Click here for full text