File #: 21-0878    Version: 2
Type: public hearing Status: Filed
File created: 9/7/2021 In control: Planning Commission
Agenda date: 9/20/2021 Final action: 9/20/2021
Title: Capital Facilities Plan, 2022-2027 Financial Plan - Public Hearing
Attachments: 1. Online link to Preliminary CFP, 2. UAC Comment Letter
Related files: 21-0838, 21-0936
Title
Capital Facilities Plan, 2022-2027 Financial Plan - Public Hearing

Recommended Action
Conduct a public hearing to accept public comment on the Capital Facilities Plan, 2022-2027 Financial Plan prior to preparing a recommendation letter for the City Council.

Report
Issue:
Public hearing to accept public comment on the Capital Facilities Plan, 2022-2027 Financial Plan.

Staff Contact:
Joyce Phillips, Principal Planner, Community Planning and Development, 360.570.3722

Presenter(s):
Joyce Phillips, Principal Planner, Community Planning and Development

Background and Analysis:
The Capital Facilities Plan (CFP) is a Chapter in the City's 20-year Comprehensive Plan. The CFP portion of the Plan is updated annually.

The CFP identifies which capital facilities are necessary to support development and/or growth, as well as major capital investments needed for city infrastructure. Most projects listed are directly related to the applicable master plan or functional plan, such as the Parks, Arts and Recreation Plan, the Storm and Surface Water Plan, Transportation Master Plan, and other similar plans.

The Comprehensive Plan covers a 20-year time horizon; however, the Preliminary CFP 2022-2027 Financial Plan is primarily a 6-year financial plan. Projects for years 7-20 are identified but cost estimates and funding sources are less certain. The CFP is required by the Growth Management Act and includes specific projects, cost estimates, funding sources and strategies to implement the plan.

Some highlights of the CFP, 2022-2027 Financial Plan include:

* Armory Creative Campus Design
* Peace and Healing Park Design
* Grass Lake Nature Park Trail Improvements
* Lions Park Sprayground Construction
* State Avenue Safety Improvements
* Fones Road Improvements (Pacific to 18th)
* Boulevard Road Trail Crossing Improvements
* Accessibility Improvements (Washington Center for the Performing Arts Building)
* Boulevard Road Reservoir Rehabilitation
* Old Port 1 Sewer Li...